Determining and Documenting Triggers for Full First Article Inspection
Published .
Related
- AS9100
Topics
- fai
- as9102
- production-lapse
- facility-relocation
- form-1
- quality-records
A manufacturing supplier experienced operational changes including facility relocation and extended delivery gaps where parts were fulfilled from existing inventory. Quality personnel evaluated whether these non-design operational events invalidated the existing baseline First Article Inspection Report (FAIR) under AS9102.
Quality teams frequently confuse purchasing inactivity with actual production lapses, or fail to formally record operational triggers such as manufacturing facility relocation as the reason for performing a full or partial FAI.
Common Mistakes
- Quality teams frequently confuse purchasing inactivity with actual production lapses, or fail to formally record operational triggers such as manufacturing facility relocation as the reason for performing a full or partial FAI.
- Treating a design change as a full FAI re-accomplishment instead of a partial/delta.
Best Practice
Track physical manufacturing completion dates rather than procurement order dates when monitoring the two-year production lapse threshold defined in AS9102. When facility moves or process source changes occur, perform a documented risk evaluation and explicitly state the operational trigger in Form 1 Field 14.
Reflects the recommended position based on community discussion and expert review.
Continue the conversation
Have a different interpretation or recent experience that adds nuance? The community keeps lessons sharp.
Ask LINK
Get an instant AS9102-grounded answer from our FAI assistant. The fastest path to a working answer for your own situation.